Step-by-Step Planning Checklist for Biogas Plants

The following table gives an overview of all the steps required to build a biogas unit. The order follows a usual time-line. There are steps which can be combined. However, to skip any of them might lead to future problems.

Customer Contractor
  organizes advertisement, awareness creation
hears about biogas, develops interest, get's in contact with the contractor  
  gives first overview over costs
  writes letter to the customer
writes a request  
  starts file
  makes a side visit, including: discussion and calculations
  makes a quantity survey,
  does object planning
  writes invoice
explains warranty performances
makes first payment (50%) organizes a customer and constructor sign contract
  hands over a list of building material to be delivered by the customer
prepares the material he agreed to deliver  
  organizes material delivery, reference line, main construction work, finishing, landscaping, slurry component, piping.
starts to fill the plant
second payment (50%)
 
  finishes piping installation of gas consumption accessories
discusses handing over  
makes an agreement on co-operation regarding fertiliser utilisation  
  makes a follow up on fertiliser utilisation
  does customer monitoring
  conducts technical and agricultural service visits