Checklist for building a biogas plant
- Finishing the planning, i.e. site evaluation,
determination of energy demand and biomass supply
/ biogas yield, plant sizing, selection of plant design, how and where to use the biogas,
etc., in accordance with the planning guide
- Stipulate the plant's location and elaborate a site plan, including all
buildings, gas pipes, gas appliances and fields to be fertilized with digested slurry
- Draft a technical drawing showing all plant components, i.e. mixing pit,
connection to stabling, inlet / outlet, digester, gas-holder, gas pipes, slurry storage
- Preparation of material / personnel requirements list and procurement of materials
needed for the chosen plant:
- bricks / stones / blocks for walls and foundation
- sand, gravel
- inlet / outlet pipes
- metal parts (sheet metal, angle irons, etc.)
- gas pipes and fittings
- paint and sealants
- gas appliances
- tools
- mason and helper
- unskilled labor
- workshop for metal (gas-holder) and pipe installation
- Material / personnel assignment planning, i.e. procedural planning and execution
of:
- excavation
- foundation slab
- digester masonry
- gasholder
- rendering and sealing the masonry
- mixing pit - slurry storage pit
- drying out the plant
- installing the gas pipe
- acceptance inspection
- Regular building supervision
- Commissioning
- functional inspection of the biogas plant and its components
- starting the plant
- Filling the plant
- Training the user